Trackpad

Ground Stabilisation Traction System

Dump-Ezy Classic Assembly and Installation Instructions

All fittings used must be Watermarked and all installations should comply with AS/NZS3500.2.2 Section 3.15.

If you are installing a septic tank system, transfer station or a treatment plant, please also refer to the instructions provided with these kits.

The Dump-Ezy can be bolted to an existing floor surface or cast into a concrete slab.

Installation Instructions

Set-in-concrete Option

  • Locate the o-ring supplied and fit it into the groove at the underside of the outlet.
  • Install the 150mm coupling by screwing it firmly up against the o-ring. Do not over tighten.
  • Assemble pipe work as per details supplied on the underside of the unit and on diagram.
  • Bed plumbing as per Standard to correct height for coupling.
  • Set formwork such that the Dump-Ezy is level and will be set into the slab no more than 50mm.
  • The slab should have fall-away from the unit.
  • For compliance with the Plumbing Standard, the minimum height of wall above ground must be 150mm.
  • Pour concrete and finish with brushed surface for wet area safety.
Note: The minimum height from invert level of the outlet to the underside of the unit is 270mm

Bolted Option

  • Position the outlet piping in with the correct minimum set-out distance from the inside face of the wall.
  • The minimum hole size required in the floor is 185mm diameter.
  • The unit must be installed on a flat and level surface.
  • Locate the o-ring supplied and fit it into the groove at the underside of the outlet.
  • Install the 150mm coupling by screwing it firmly up against the o-ring. Do not over tighten.
  • Assemble pipe work as per details supplied on the underside of the unit and on diagram.
  • Position the Dump-Ezy on the floor, mark around the unit and mark fixing positions. There are 10 fixing holes in the unit which accept 10mm fasteners with 25mm washers.
  • Place a large bead of caulking material on the floor just inside the line. Complete the pipe joint and then fix the unit in position. Clean up any excess caulking material.
  • For compliance with the Plumbing Standard, the minimum height of wall above ground must be 150 mm. (Dump-Ezy wall is 200mm high)
  • Note: All mechanical fixings should be Stainless Steel.
Required Pipework Assembly Details O-ring is supplied

Pipework and Fittings

Pipe work and fittings should be checked as per standard plumbing guidelines. Fittings should be inspected for leaks at joints and tank connections. If a backflow prevention device is installed on the hose cock, it will require inspection and certification under AS 3500.

Locking

If required, the Dump-Ezy unit has an in-built locking point at the front below the handle. The lock required to fit the unit is a “Lockwood” product code no 234/45. This lock can be keyed alike.

Optimal Installation Diagrams and Checklist

Dump-Ezy Installation Checklist
Optional Installation Levels
Optional Installation Bi-directional

Thank-you for choosing the Dump–Ezy unit

Should you have any problems with installation of this unit, please do not hesitate to contact:
Gough Plastics on freecall 1800 069 805, (International 61 7 4774 7606) or your local distributor.